Mafra
Ericeira | Praia do Algodio reopens after cliff stabilization works completed
Praia do Algodio in Ericeira reopened to the public after cliff stabilization works finished. The Captain of the Port of Cascais lifted the ban that had been in place since 9 February.
The closure followed a rockfall and heavy rain that worsened cliff instability. The Agência Portuguesa do Ambiente carried out the 1.1-million-euro project, funded by the PACS programme, which removed loose blocks, installed anchors and coated the cliff face.